Page 1 of 1
Payables R12
Posted: Thu Nov 26, 2009 6:42 am
by sree02.oracle
Version R12
Instance PROD/TEST =
Module? =
OS? =
Hi Team,
I've a case it need to be setup in applications R12.
Can anyone share the solution or how to configure in the appln?
Case as follows " Company takes loan and issues Post dated cheques for the equal months"
company is going for financials, projects and S and D modules.
Thanks in Advance..
Posted: Fri Nov 27, 2009 9:21 am
by karthikeyanp1981
Dear Sree,
Frankly speaking i have no idea on this, however the feature of Future Dated Payments covers the aspect of Post Dated Cheques.
The maximum setups one requires is to have a bank account that support future dated payments.
Then shedule the payments for the future dates, as and when your load holders encashes the cheque, bank will release the payment, and you will come to know about it during reconciliation process.
I am not sure about any additional steps such as running special concurrent programs is required or not. However i request you to read the Future Dated Payments feature and setups related to it in detail from the user guide and make an attempt in the test or vision instance.
How it actually works is what matters the most, than what has been written ...
Regards,
Karthikeyan
Posted: Sun Nov 29, 2009 11:50 pm
by tgs100
If you are looking for issuing PDC cheques, then future dated payment functionality in AP will suffice. If you want rich loan functionality, then you can explore oracle loan module.
Cheers,
Saravanan